Hi Experts,
While doing completion of operation in SAP ME, the confirmation is getting posted in ECC.
However, no activities such as machine/ labor time are getting posted with the operation confirmation.
Requirement is to have the confirmation of activities along-side to ensure cost re-conciliation for internal activities.
Please suggest what could be possibly done in order to achieve the desired results.
Regards
Ravi Gupta